Improve statewide mobility of people, goods and services
Indicator 10: Transportation projects completed on time and on budget
Measure a: Percent of Nickel and TPA Projects Competed on Time and On Budget, Cumulative to Date 2003 to June 30, 2008
Description:
On-Time refers to the project being operationally complete within the quarter as planned in the original Legislative expectation (2003-05 Nickel, 2005-07 TPA). On-budget refers to the project being within +/- 5 percent of the current Legislative expectation (baseline).
| Percent of Nickel and TPA Projects Competed on Time and On Budget, Cumulative to Date 2003 to June 30, 2008 | |
| Percent Completed Early or On-Time | 89% |
| Percent Completed Under or On-Budget | 86% |