Improve statewide mobility of people, goods and services

Indicator 10: Transportation projects completed on time and on budget

Measure a: Percent of Nickel and TPA Projects Competed on Time and On Budget, Cumulative to Date 2003 to June 30, 2008

Description:

Percent of Nickel and TPA Projects Competed on Time and On Budget, Cumulative to Date 2003 to June 30, 2008

On-Time refers to the project being operationally complete within the quarter as planned in the original Legislative expectation (2003-05 Nickel, 2005-07 TPA). On-budget refers to the project being within +/- 5 percent of the current Legislative expectation (baseline).

Percent of Nickel and TPA Projects Competed on Time and On Budget, Cumulative to Date 2003 to June 30, 2008
Percent Completed Early or On-Time
89%
Percent Completed Under or On-Budget
86%

Source:

Department of Transportation-Gray Notebook